Welcome back to our #32Thursday #ConstructionUpdate 🥳
Things on site are buzzing, here’s just a small taste of what @localworksug has been up to:
🚧 Our café is looking extra fresh now that the wooden form-work for the rammed earth has been removed
🚧 First door sample is installed! The team is now working on getting the sliding and locking mechanism just right
🚧 The columns for the studio walkway are being set up
🏁 And last but not least, we’re on our way to milestone 5 with the roofing phase of construction now underway!
It’s all taking shape with Phase 1 still on course for completion in October. So exciting!